Our windlass is a vital part of our boat as it controls our anchor and anchor chain. It allows us to use the motor to raise and lower our 100 meters of 10mm stainless chain and 33 kilo spade anchor. We replaced the motor, gaskets and a few other small pieces in Costa Rica 2019, but we have not taken the top portion of the windlass apart for some time.
We were having issues with the windlass as it was drawing too much power to operate. Something was causing friction or issues making the motor work too hard which then overloaded the batteries. Never a good thing to have the boat shut down as you are trying to bring up the anchor.
Getting Started
In order to work on the windlass we have to disengage the anchor chain. However, we did not want it to drop into the marina water so we ended up securing the anchor and chain to the bow roller.
We ordered new gaskets, o-rings, a sure clip, and a bearing from Lewmar (which took forever to arrive). As Matt was taking everything apart he realized that the spacer had rotted. Well shoot! For some reason, Lewmar has stainless and aluminum pieces put together which is odd as these two materials don’t like each other.
End of Year Delay
New problem. This spacer was not available anywhere in NZ, USA, or Europe! Evidently Lewmar would not be manufacturing more of these pieces until end February (it was December when we discovered the problem). If we were to wait, the part would not get to us until April or May. That would mean that we could not leave the marina as we would have no means to anchor which was simply unacceptable. So, we decided to take it to RH Precision Engineering to have a new one fabricated.
Rob at RH Precision was wonderful! We dropped the sad little spacer off on Friday before Christmas and he called us on Wednesday 28 Dec to tell us it was ready! And on top of that he only charged us $100NZD and 2 beers! We would have spent hundreds of dollars more had we ordered it from Lewmar. And it is beautiful and works perfectly!
We discovered the culprit was a rotted cord deck which held the spacer. Sea water had seeped into the wood, rotted it out and kept the spacer wet. So, Matt had to dig out all of the rotted wood, let it dry out, then filled it with epoxy.
We were finally able to complete the windlass project after 3 weeks, mostly waiting on parts. Now, we should be able to anchor without putting too much stress on our batteries.